SNO process hits crucial stage

Rodney Weidemann
By Rodney Weidemann, ITWeb Contributor
Johannesburg, 02 May 2003

The department of communications is hoping that the process for selecting a second national operator (SNO) to be awarded the fixed-line telephone licence will go smoothly from here, with August 8 the target date for a recommendation to be made to the minister.

Pakamile Pongwana, deputy communications minister and chairman of the SNO working committee, which will be conducting one-to-one discussions with the various bidders, says this is not, however, a definite date.

"The guideline we are working towards is to move to the next phase - making our recommendations to the Independent Communications Authority of SA (ICASA) - within a month. Then we hope that ICASA will make its recommendation for the licence by August," says Pongwana.

"This is, however, not a date that can be set in stone as the process will still involve much discussion and negotiation, so the dates may yet change."

The bidders

The department announced the names of four of the five bidders for the SNO licence on Wednesday afternoon. The fifth consortium`s name, from China, was not made known, although it is widely believed to be spearheaded by Shanghai Telecom.

The bid will first have to undergo clearance because of fears regarding the possible transmission of Severe Acute Respiratory Syndrome (SARS).

One of the other four bidders is TeleAccess Investments, a company which operates the SNO in Zimbabwe and has a major interest in the Comtel . Comtel seeks to provide communication links between 21 African countries and will be built on a combination of optic , microwave links and satellite connections that will allow for , data and video transmissions.

Also in the running is CommuniTel, which includes the former Goldleaf consortium that made a failed bid during the first bidding process.

It now also includes Telecom Namibia, the Umkhonto We Sizwe Military Veterans Association (MKMVA), Gateway Communications (UK/South Africa) and Premier Contracts Agency (PCA) from the UK.

According to CommuniTel, it also plans to have BritishTelecom (BT) involved in the project and the consortium is looking at ways that BT can invest a significant amount of money into SA without compromising itself through taking an equity stake in the SNO.

The third bidder is Two Consortium, which is understood to include Norwegian operator Telenor. Telenor, along with fellow Scandinavian operator Telia, bid for the third cellular licence several years ago.

European operator Swedtel is also thought to be involved with Two Consortium. Telia maintains a large shareholding in the Swedtel operation.

T-Systems, an ICT service provider within the Deutsche Telekom group, is the fourth bidder along with its sister company, Detecon International. Detecon has handled management contracts for several African telephony projects.

The T-Systems/Detecon International consortium is understood to be approaching the issue from a management contract perspective, rather than an outright purchase of the 51% stake on offer. This could mean that the group may form part of a merged consortium that would be recommended to ICASA.

Possible mergers

Pongwana has already stated that the SNO working committee may possibly have to facilitate a merger between some of the bidding parties in order to get the best elements from each combined into one strong entity.

"It may be that one of the bidders has a strong financial element, while another has good business skills, for example," he says.

"We will then negotiate with them and see if it will be possible to combine them into a single new consortium that will provide SA with a strong equity owner and therefore a good SNO."

Asked what would happen if ICASA chose to reject the bid or bids that the working committee passed on to it - as happened in the first round of bidding when both the Goldleaf and Optis bids were rejected - Pongwana said they would cross that bridge when they came to it.

"We will obviously have to look at our options and analyse the issues if that should happen. We may then have to look at another route for deciding who will be awarded the SNO licence, but only if such a route is provided for by the law."